Marks & Spencer – Food Halls 20 Stores

Project Details

PROJECT TITLE

Marks & Spencer – Food Halls 20 Stores

CLIENT

​Marks & Spencer

MAIN CONTRACTOR

Eco-1

ECO-1 ROLE

Main Contractor

DURATION

20 weeks

PROJECT VALUE

£900,000.00

SECTOR

Retail

Works Undertaken

The project was a roll out to a large number of stores within mainland UK, comprising of high street, retail park & outlet stores within the M & S Estate.

Eco-1 were appointed as main contractor and designer to install a new linear LED lighting system scheme, LED panels and downlights within the food halls, replacing an outdated system and upgrading the controls philosophy.

Unique to this project was the design element, advising the client of the best ways of utilising the existing lighting control system and working with the fabric of the buildings, to give the best scheme in terms of being aesthetically pleasing, future proof and energy saving.